Anyone who has traveled on I-75 North through Caryville has been frustrated by the delays caused by the construction being done to widen the road to three lanes in either direction. Then project was being worked on by Huntsville’s Potter South East LLC. The project has been underway since 2016 and was scheduled to have been completed in May of this year.

Now TDOT is seeking a replacement contractor to bid on and complete the project which is less than 60% complete. The deadline to bid on the project is November 16th. Terms of the bid are that the project is to be completed by September 30, 2019.